The Challenge
An independent waste management and energy-from-waste facility experienced a failure of a critical dry air cooler that had reached the end of its service life. Specialist parts were required and had to be sent away for a full repair, leaving the site without a key piece of cooling equipment.
With the dry air cooler playing a vital role in maintaining operational stability, a temporary solution was required to avoid disruption. The replacement also needed to be installed quickly and safely, requiring a crane lift and rapid mobilisation.
Cross Rental Services Solution
Cross Rental Services supplied a like-for-like temporary dry air cooler, ensuring the unit matched the performance and capacity of the existing system.
A crane lift was organised and completed within 48 hours of the initial client contact, allowing the temporary equipment to be installed without delay. The unit was then integrated into the existing system, enabling the facility to continue operating efficiently while the new permanent dry air cooler was delivered and installed.
The Outcome
The rapid deployment of a temporary dry air cooler ensured the site remained fully operational, avoiding unplanned downtime and maintaining critical processes throughout the repair period. The seamless integration and fast response allowed the client to continue operations with confidence until the permanent replacement was installed, demonstrating Cross Rental Services’ ability to deliver reliable, time-critical cooling solutions.
Gallery
Overview
- End-of-life dry air cooler required urgent replacement
- Like-for-like temporary unit supplied to maintain performance
- Crane lift arranged and completed within 48 hours
- Seamless connection to existing system
- Zero downtime to critical operations