The Challenge
Our client required a quick turnaround to restore heating and hot water to a school after a boiler breakdown. It was essential to provide a rapid service as without heating and hot water the school would have to temporarily close.
In addition to the time restraints for the install; our client had a small footprint area with access restrictions meaning we would be required to provide a bespoke built unit to provide required duty whilst remaining low footprint.
The Solution
- To meet the duty requirements of the client we provided our 300kw boiler which has both heating and hot water capabilities; therefore restoring equivalent services to the school with no further disruption.
- We provided a site survey to determine site requirements; before delivering and installing our boiler unit – our nationwide team and service allows us to have an engineer onsite within hours of initial contact.
- The 300kw boiler is bespoke built by our engineers specifically for sites of this nature where a containerised solution isn’t viable. The unit is slimline and can easily be moved into position on a pallet truck or forklift; which was ideal for this site.
- Heras fencing was also provided due to the units location in a school setting; ensuring a safety precaution for the school.
The Outcome
As a result of a fast turnaround survey, delivery and install by our nationwide team we were able to restore heating and hot water to the school; keeping their downtime and risk of closure to an absolute minimum.
The 300kW is able to produce the required duty effectively providing the client with a suitable solution whilst maintenance and replacement of their boiler plant room is carried out. Our bespoke fleet of boilers allowed us to overcome space and access challenges; specifically created for ease of placement in small sites meaning that we can provide high output boilers in smaller units.
Overview
- Small footprint to overcome restricted access
- Quick nationwide delivery to site
- Heras fencing for safety precaution